COMMERCIAL GRAIN STORE

7/06/2021

We subcontracted to Luddon Construction to manufacture and fit out the 200,000 ft2 commercial grain store building with steel frame and concrete external cladding. We also designed, manufactured and supplied 6 internal storage bunkers & 6 bespoke pre-cast escape tunnels including sloping roof caps, ahead of programme.

We used 1150 x 180mm pre-stressed panels and created 6 x bespoke pre-cast tunnels.



Back to all Case Studies