Our Expansion Plans

10th September 2018

We have had a very busy summer with the launch of our new range of products and our site has really started to take shape.

Our new factory build is nearly complete for us to produce our new range of precast concrete products. The 650 kw biomass landed into the new boiler room at the beginning of the month and by the end of the month we will have it fully operational to make sure that we are protecting our environment as much as we can.

A new purpose built welfare facility is now being fabricated and will be erected and fitted out over the next month or so, this will give our teams an improved environment with new canteen, drying room and car parking facilities.

Our new electronic gate and access barrier has now been fitted and fully installed with key fob access and intercom for inbound deliveries, this gives us better control for vehicles coming on to site and also helps with traffic management plans that we are putting into place.

Although we are not fully commissioned in the new precast factory as yet, the team have still managed to pour precast products in the existing factory.

We generated interest in our new products at the Highland show and I’m pleased to say that we have had our first loads of A walls, loaded and delivered to one of our customers on the East Coast.

We are delighted with how hard our team have worked to pull off the expansion and launch of our new products at such a busy time.